The list below identifies capital construction projects for roads (including streetlighting, traffic signals and sidewalks) bridges & culverts and parks & trails. Contact the Engineering Services Department for more information.

Projects where the Region of Durham is the lead proponent, involving upgrades to City infrastructure, are indicated as such. 

The Region of Durham Works Department provides other essential municipal services to residents and businesses within Durham Region, including construction, design, and environmental assessment projects that are not captured below. Please visit the Region of Durham website to search current projects and studies, and view their project map.

Capital Projects

Project  Description  Status Contractor

Request for Tender No. T2024-1

Rouge SWM Pond Sediment Cleanout

 

Sediment removal, general maintenance and restoration at the Rouge Stormwater Management Pond on Valley Ridge Crescent. To be completed by Fall 2024

Notice of Construction Cardan Demolition & Excavation Inc.

Request for Tender No. T2024-2

Asphalt Resurfacing on Various City Streets

Hillcrest Road – from Oklahoma Drive to Vicki Drive

Notice of Construction  Viola Management Inc. 
 

Edmund Drive – from Steeple Hill to Sheppard Avenue

Notice of Construction   
 

Storrington Street – from Listowell Crescent to Glenanna Road

Notice of Construction   
 

Old Orchard Avenue – from 160m east of Douglas Avenue to Liverpool Road

Notice of Construction   
 

Heathside Crescent – from Glenanna Road to 240m south to Longbow Drive

Notice of Construction  
 

Bainbridge Drive – from Burnside Drive to Marshcourt Drive

Notice of Construction   
 

Foxwood Trail – from Bayfield Street to Strouds Lane

Notice of Construction   
 

Yeremi Street – from Oklahoma Drive to Breezy Drive

Notice of Construction   
 

Bushmill Street – from Maple Ridge Drive to Liverpool Road

Notice of Construction  
 

Pickering Parkway – from 480m east of Valley Farm Road to Dreyber Court

Notice of Construction   
 

Denvale Drive – from Strathmore Crescent to Greenmount Street

Notice of Construction   

Request for Tender No. T2024-9

Sideline 24 Hard Surfacing from Highway 407 to Whitevale Road

 

Asphalt Paving of Sideline 24 from Whitevale Road to the Highway 407 Overpass Notice of Construction IPAC Paving Ltd.

Request for Tender No. T2024-5

Granite Court Proposed 1.8m Concrete Sidewalk

 

Removal of existing asphalt sidewalk and replacement with 1.8m concrete sidewalk including localized grading, restoration and pedestrian handrail.

Notice of Construction VBN Paving Ltd.

Request for Quotation No.
Q2024-36

Aspen Road Retaining Wall Replacement

 

Aspen Road Retaining Wall Replacement. The work includes removal and replacement of the existing retaining wall and chain link fence adjacent to it, installation of continuous perforated sub-drain, removal and replacement of existing concrete sidewalk and associated asphalt and topsoil/sod restoration.  

Notice of Construction Avion Construction Group Inc.

Request for Tender No. T2024-7

Beachfront Park Master Plan (Phase 1 implementation) and Alex Robertson Park Gravel Parking Lot 

 

 

Request for Tender No. T2024-7 for the award of the Beachfront Park Master Plan Phase 1 implementation which encompasses the area between Lake Ontario and Hydro Marsh, from Millennium Square to Alex Robertson Park. Work in this area includes the construction of an elevated walkway and cycling route, viewing platforms overlooking Hydro Marsh, barrier free access ramps from the elevated structure to the beach, site lighting and furniture, and additional Lake Ontario shoreline protection work from the existing water play area to the west side of Millennium Square. Work also includes the construction of a gravel parking lot in Alex Robertson Park which will initially act as the construction staging area for the Beachfront Park work. Ongoing Completion in June 2025 Rutherford Contracting Ltd.

Request for Quotation No. Q2024-33

Valley Plentiful Community Gardens Parking Area and Expansion

 

Quotation No. Q2024-33 for the Valley Plentiful Community Gardens Parking Area and Expansion, located in Diana, Princess of Wales Park, directly south of Kingston Road. Spring 2025 Kon-Strutt Construction

Request for Tender No. T2023-7

Playground Reconstruction

including playground equipment replacement 

Playground reconstruction including playground equipment replacement in Rick Hull Memorial Park, Valleyview Park, Progress Frenchman’s Bay East Park, Forestbrook Park, St. Mary Park, and Southcott Park. To be completed by summer 2024. Complete Gray's Landscaping & Snow Removal 

Request for Tender No. T2023-14

Tennis Court Expansion – Shadybrook Park

 

Tennis Court Expansion – Shadybrook Park

Construction of one additional tennis / 4 pickleball court (shared facility) in Shadybrook Park. Construction to be completed by fall 2024.

Complete Zilli Construction Ltd. 

Waterfront Trail Reconstruction – Elvira Court to Bruce Handscomb Park

Widening and realignment of the waterfront trail from Elvira Court to Bruce Handscomb Park, including replacement and upsizing of the stream culvert, lighting and site restoration. Construction to be completed by summer 2024.

Complete Toronto and Region Conservation Authority 

Last update to this page: January 21, 2025

Contact Us

Engineering Services
One The Esplanade
Pickering, Ontario
Canada L1V 6K7

905.420.4624

Email Engineering Services